Saint-Gilles swimming pool will not reopen before summer 2027

10:41

The Victor Boin swimming pool in Saint-Gilles will not reopen until the middle of next year at the earliest, about 18 months later than planned.

The building dates from 1905 and had not been thoroughly renovated since the 1930s. 

It closed on 1 July 2023 for work to shore up its structure, insulate the roof and carry out other repairs.

The job was supposed to take 30 months, which would have meant reopening early in 2026, and cost €9.6 million.

That timetable slipped when workers found that the metal beams supporting the old Turkish baths had rusted.

All of them had to be replaced, adding six months to the work and pushing the bill up to about €13 million.

Then, during tests on the water filtration system last summer, another problem came to light.

Fixing it will cost €700,000, which is to be included in the commune's 2027 budget and still has to be approved by the municipal council.

"The work is in its final phase, fortunately," Loes Salomez (Groen), the alderwoman responsible for municipal property, told Bruzz.

But Salomez could not put a date on the reopening, adding: "There are still too many factors we're uncertain about."

Putting the filtration right "takes a big bite out of our budget," Salomez added.

According to DH, sports alderman Saïd Ahruil (PS) also mentioned a crack in the pool, which was quickly repaired.

Once the work is finished, probably in the coming weeks, Ahruil will have to set the new range of services and the prices.

That is expected to take several months, which makes a reopening before summer 2027 unlikely.

For Salomez, the delay matters beyond sport. "Reopening a swimming pool isn't only about reopening a sports facility.

A pool contributes to people's health, safety and quality of life, "especially for children, who must have the chance to learn to swim," she added.

Written by Nick Amies